Documenting the building of new houses at 189 Bunker Hill, Stratham, NH 03885.

Latest 5 Posts

Lots of progress this week, they've been putting the hours in.

Now know what the weird structure was for - making the roof. Not seen it done that way before.

Wed Apr 16 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Wed Apr 16 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Thu Apr 17 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Thu Apr 17 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Thu Apr 17 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Thu Apr 17 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Sat Apr 19 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Wed Apr 16 2025 00:00:00 GMT+0000 (Coordinated Universal Time)

Despite the bad weather framing and exterior walls have been going up. Not sure what the structure on the red zip-panels is yet

Thu Apr 03 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Thu Apr 03 2025 00:00:00 GMT+0000 (Coordinated Universal Time)

Despite the bad weather framing and exterior walls have been going up.

Thu Apr 03 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Thu Apr 03 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Fri Apr 04 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Fri Apr 04 2025 00:00:00 GMT+0000 (Coordinated Universal Time)

Guess I will never know what the basement floor is, but they've been hard at work getting the main floor in.

Tue Mar 25 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Wed Mar 26 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Wed Mar 26 2025 00:00:00 GMT+0000 (Coordinated Universal Time) Thu Mar 27 2025 00:00:00 GMT+0000 (Coordinated Universal Time) 2025/03/28

Not sure what the floor is. Looks more like gravel than concrete.

Tue Mar 18 2025 00:00:00 GMT+0000 (Coordinated Universal Time)