No flying yesterday as Kamala Harris was at Throwback, and I don't want to annoy the FAA.
Whole drainage area must be done for now as they've sprayed it with Hydroseed.
Looks like they're getting on with the roadway, and possibly some work up near the road?


Spillway looks about done, with two drainage pipes and starting to fill with sand.
They're also working on the roadway drainage to the stormwater pool.

More detail on the catchment area, and it looks like they're making the spillway for overflow.
Also saw they're putting in the pipes for running electricity and cable.

They've started digging out the catchment basement for the stormwater runoff from the roadway.
The roadway is also looking a lot more complete - they might have all the pipes in there, didn't catch them.

The big rock is still there, but they have excavated around it.
More levelling for the turning circle, with the roller vibrating and shaking our house.
Nothing much has changed, apart from more hammering of large rocks.
Also some levelling of the turning circle.